PCCM Works Review: Plan Head 53

A Detailed Project-by-Project Analysis

Status as of June 25, 2025

Mumbai Division, Central Railway

Agenda

  1. High-Level Summary: Overall project status and key highlights.
  2. Goods Shed & Parcel Depot Modernization: Detailed review of freight and parcel infrastructure projects.
  3. Major Redevelopment Projects: Focus on CSMT, LTT, Lonavala, and the Amrit Bharat Station Scheme (ABSS).
  4. Amrit Bharat Station Scheme (ABSS) - Deep Dive: Project-wise status for all 15 ABSS stations.
  5. General Passenger Amenities: Progress on FOBs, Lifts, Platforms, and other key works.
  6. Project Pipeline & Closure: Review of new works, deletions, and short closures.
  7. Conclusion & Way Forward.

Overall Project Status - A Snapshot

A total of 177 works are sanctioned under Plan Head 53, indicating a massive investment in customer amenities. The portfolio is dynamic, with numerous projects at every stage of the lifecycle.

StatusNo. of WorksPercentageRemarks
Physically Completed4726%9 of these are under process for final deletion.
Work in Progress7945%Includes major ongoing schemes like ABSS and CSMT upgrade.
LOA Issued32%Contracts awarded, work to commence.
Tender Stage42%Includes TC Process (2) and Tender Floated (2).
Approval Stage42%GAD (General Arrangement Drawings) under approval.
Estimation Stage4023%Includes Vetting (14) and Preparation (26).
Total177100%

Key Strategic Pillars

Our efforts are concentrated on three strategic pillars to deliver a transformational impact on passenger and freight customer experience.

1. World-Class Hub Development

CSMT Major Upgradation: A landmark project to redevelop CSMT into a global standard terminal.
Cost: ₹1,813 Cr.
Executing Agency: RLDA

2. Amrit Bharat Station Scheme

A comprehensive scheme for the modernization of 15 key stations across the division with a focus on holistic development.
Scope: Buildings, platforms, FOBs, lifts, escalators, and aesthetics.

3. Freight Infrastructure Modernization

Targeted upgrades of Goods Sheds and Parcel Depots to improve efficiency, capacity, and amenities.
Key Locations: Kalyan, LTT, Turbhe, Nagothane, Taloja.

Section 2

Goods Shed & Parcel Depot Modernization

Enhancing Freight and Parcel Handling Capabilities

Goods Shed Program - Overview

Significant investments are being made to upgrade infrastructure at key goods sheds under the PWP 2022-23 & 2023-24 programs.

LocationEstimated Cost (₹ Cr)Status
Kalyan (KYN)23.05TC Process
Turbhe (TAPG)13.28Work in Progress
Nagothane (NGTN)10.67Work in Progress
Taloja (TPND)7.99 + 17.65WIP / Estimation
Trombay (TMBY)34.05Sanctioned
New Mulund (NGSM)30.35Proposal with Rly. Board
Bhiwandi Road (BIRD)33.34Proposal with Rly. Board
General Lighting4.99Work in Progress
CCTVs6.75Sanctioned

Goods Shed - Kalyan (KYN)

  • Project Name: Improvement of Goods Shed at Kalyan (KYN)
  • Estimated Cost: ₹23.05 Crores
  • Sanctioned: December 13, 2024
  • Scope of Works:
    • Improvement of covered shed area (COP, side walls, platform resurfacing).
    • Provision of new covered shed for 23 wagons.
    • Improvement of circulating area and approach road with cement concreting.
    • Reconstruction of culvert and improvement of drainage.
    • New G+1 building for Labour/Merchant rooms.
    • Provision of water sprinklers, dust screens, CCTVs.
  • Current Status: Tender Opened on May 13, 2025. TC Minutes are under process.
  • Executing Agency: GSU / BB

Goods Shed - Turbhe (TAPG)

  • Project Name: Improvement of Goods Shed at Turbhe (TAPG)
  • Project ID: 01.02.53.23.1.55.036
  • Anticipated Cost: ₹14.98 Crores
  • Status: Work in Progress (30% complete)
  • Scope of Works:
    • Provision for full-length BCNHL rake by relocating rooms.
    • Replacement of old COP, valley gutters, and down-take pipes.
    • Resurfacing of platform.
    • New G+1 building for Labour/Merchant rooms with amenities.
    • Improvement of drainage system.
  • Remarks: LOA issued on September 23, 2024. Work is progressing. TDC: Dec 31, 2025.

Goods Shed - Nagothane (NGTN)

  • Project Name: Improvement of Goods Shed at Nagothane (NGTN)
  • Project ID: 01.02.53.23.1.55.037
  • Anticipated Cost: ₹12.04 Crores
  • Status: Work in Progress (25% complete)
  • Scope of Works:
    • Improvement of approach road and circulating area with cement concreting.
    • Provision of new G+1 building for Labour/Merchant rooms.
    • Provision of stacking shed.
    • Enhanced drinking water and bathing facilities.
  • Remarks: LOA issued on September 23, 2024. Work is progressing. TDC: Dec 31, 2025.

Goods Shed - Taloja Panchanand (TPND)

Project 1: Full Length COP

  • Project ID: 01.02.53.22.1.51.006
  • Cost: ₹7.99 Crores
  • Status: Work in Progress (90% complete)
  • Scope: Provision of full-length COP on high-level platform & drainage system.
  • Remarks: Erection of COP shed is in progress. TDC: June 30, 2025.

Project 2: Additional Line & Relocation

  • Project ID: 01.02.53.24.3.51.019
  • Cost: ₹17.51 Crores (Est.)
  • Status: Under Finance Vetting
  • Scope: 700m additional line, relocation of office to new G+2 building.

Goods Shed - Trombay (TMBY)

  • Project Name: Improvement of Goods Shed at Trombay (TMBY)
  • Project ID: 01.02.53.24.1.51.002
  • Estimated Cost: ₹34.05 Crores
  • Sanctioned: May 16, 2025
  • Scope of Works:
    • Extension of existing handling line (from 500m to 725m).
    • Extension of existing sick line (from 225m to 725m).
    • Provision of a new high-level platform (700m x 20m) with COP.
    • Provision of a new G+1 building (40m x 30m) for offices and rooms.
  • Current Status: Sanctioned. Detailed estimate is under preparation.
  • Executing Agency: Open Line

Goods Shed - Proposals with Railway Board

New Mulund (NGSM)

  • Estimated Cost: ₹30.35 Crores
  • Proposed Scope: Major improvements to approach road, circulating area, platforms, drainage, and COP. Includes provision for new offices and amenities.
  • Status: At Railway Board for sanctioning.

Bhiwandi Road (BIRD)

  • Estimated Cost: ₹33.34 Crores
  • Proposed Scope: New approach roads, a G+2 service building, parcel stacking shed, and retaining walls.
  • Status: Proposal with Railway Board since March 15, 2025. Remarks on queries are being prepared.

Goods Shed - General Amenity Works

Project: Improved Lighting

  • Project ID: 01.02.53.23.1.55.034
  • Cost: ₹4.99 Crores
  • Status: Work in Progress (10% complete)
  • Scope: Improvement of goods shed and yard lighting by providing additional high mast towers and indoor LED fittings.
  • Remarks: Tender awarded on Nov 14, 2024. Material mobilization is in progress.

Project: CCTVs

  • Project ID: 01.02.53.24.3.51.025
  • Cost: ₹6.75 Crores
  • Status: Sanctioned, estimate under preparation.
  • Scope: Provision of 198 CCTVs at 11 Goods Sheds and 6 Parcel Depots.

Parcel Depot Program - Overview

Lokmanya Tilak Terminus (LTT)

  • Project: Construction of 3 Big Warehouses
  • Cost: ₹17.83 Crores
  • Status: Under Finance Vetting

Wadi Bunder (WB)

  • Project: Provision of Parcel Siding Platform
  • Cost: ₹14.54 Crores
  • Status: Under Finance Vetting

LTT, Panvel, Wadi Bunder

  • Project: Parcel Management System (PMS)
  • Status: PMS at LTT (Ph-II) & Wadi Bunder (Ph-III) are awarded. PMS at Panvel (Ph-I) is complete.

Parcel Depot - Lokmanya Tilak Terminus (LTT)

  • Project Name: Construction of Big Warehouses with cement concreting flooring
  • Project ID: 01.02.53.24.3.51.010
  • Estimated Cost: ₹19.50 Crores
  • Scope: Construction of 3 warehouses with a total approximate size of 7550 Sqm.
  • Current Status: Sanctioned by GM on March 31, 2025. The detailed estimate is under preparation.
  • Executing Agency: Open Line / BB

Parcel Depot - Wadi Bunder (WB)

  • Project Name: Provision of parcel siding rail level platform
  • Project ID: 01.02.53.24.3.51.018
  • Estimated Cost: ₹14.54 Crores
  • Scope:
    • Provision of a parcel siding platform (200m x 15m).
    • Cemented circulating area (200m x 20m).
    • Pathway across and between stabling lines.
  • Current Status: Sanctioned by GM on March 31, 2025. The detailed estimate is under finance vetting.
  • Executing Agency: GSU / BB

Section 3

Major Redevelopment & ABSS

Transforming Stations into City Centres

CSMT Major Upgradation

  • Project Name: Major upgradation of Chhatrapati Shivaji Maharaj Terminus (CSMT)
  • Project ID: 01.02.53.23.1.84.031
  • Anticipated Cost: ₹1,813 Crores
  • Executing Agency: RLDA
  • Status: Work in Progress (2% complete)
  • Key Milestones:
    • EPC Contract Awarded: April 28, 2023 (to M/s Ahluwalia Contracts).
    • Contract Agreement Signed: June 1, 2023.
    • PMS Appointed: July 6, 2023 (SYSTRA-MACE).
    • Appointed Date Declared: July 10, 2023.
  • Current Activity: 32 structural assessments are in progress.

LTT & Lonavala Redevelopment - Consultancy

  • Project Name: Appointment of technical consultant for Techno-Economic feasibility studies and Master Planning for redevelopment of LTT & Lonavala stations.
  • Project ID: 01.02.53.22.3.55.001
  • Cost: ₹1.79 Crores
  • Status: Work in Progress (50% complete)
  • LTT Status:
    • Consultancy contract awarded on Oct 3, 2022.
    • The master plan has been approved by GM and sent to the Railway Board on May 11, 2023. Awaiting a presentation date.
  • Lonavala Status:
    • Booklet (KD3) submitted.
    • GM has instructed to prune down the cost after reviewing the master plan concepts.

Amrit Bharat Station Scheme (ABSS) - Overview

Modernization of 15 stations is underway in Mumbai Division under ABSS, with a focus on improved amenities, accessibility, and aesthetics.

Station CategoryNames of Stations
Phase 1Byculla, Chinchpokli, Parel, Matunga, Kurla, Vidyavihar, Vikhroli, Kanjurmarg, Mumbra, Diva, Shahad, Titwala, Igatpuri, Wadala Road, Sandhurst Road.

Key Project Components:

  • Station Building Upgrades & Facade Improvements
  • New Foot Over Bridges (FOBs)
  • Provision of Lifts & Escalators
  • Platform Improvements (Flooring, Shelters)
  • Improved Signage, Toilets, and Waiting Areas
  • Horticulture & Vertical Gardens
  • Provision of Sewage Treatment Plants (STPs)

ABSS - Station Buildings (Group 1 - Completed)

Parel (LB-1943):

Cost: ₹8.58 Cr | Status: 100% complete.

Vadala Road (LB-1963):

Cost: ₹8.04 Cr | Status: 100% complete.

Matunga (LB-1961):

Cost: ₹5.34 Cr | Status: 100% complete.

Chinchpokli (LB-1959):

Cost: ₹6.44 Cr | Status: 100% complete.

Byculla (LB-1958):

Cost: ₹11.82 Cr | Status: 100% complete.

ABSS - Station Buildings (Group 2 - WIP)

Vikhroli (LB-1964):

Cost: ₹10.55 Cr | Status: 85% complete.
Remarks: New facade, service building finishing, and parking work in progress.

Diva (LB-1960):

Cost: ₹18.62 Cr | Status: 80% complete.
Remarks: Work on west side toilet block and new service building is in progress.

Sandhurst Road (LB-1962):

Cost: ₹10.37 Cr | Status: 70% complete.
Remarks: False ceiling work and extension of elevated booking office in progress.

Mumbra (LB-1957):

Cost: ₹8.70 Cr | Status: 71% complete.
Remarks: Column erection for passage and facade is in progress.

ABSS - Station Buildings (Group 3 - WIP)

Kanjurmarg (LB-1950):

Cost: ₹4.96 Cr | Status: 95% complete.
Remarks: West side circulating area and service building work in progress.

Vidyavihar (LB-1965):

Cost: ₹7.28 Cr | Status: 60% complete.
Remarks: Work on home platform and new drain is in progress.

IGP, CLA, TLA, SHAD (LB-1967):

Cost: ₹24.97 Cr | Status: 55% complete overall.
Breakdown: Igatpuri (60%), Kurla (85%), Shahad (100%), Titwala (96%).

ABSS - Foot Over Bridges (FOBs) - Part 1

Byculla FOB (LB-1940):

Cost: ₹11.33 Cr | Status: 30% complete.
Remarks: Column erection completed. Girder fabrication completed and splicing is in progress at site. TDC: June 30, 2025.

Kanjurmarg FOB (LB-1942):

Cost: ₹12.68 Cr | Status: 20% complete.
Remarks: Column erection is in progress. Girder material is under procurement. TDC: Aug 31, 2025.

Vidyavihar FOB (LB-1937):

Cost: ₹12.24 Cr | Status: 10% complete.
Remarks: Column erection is in progress. Girder material is under procurement. TDC: Sep 30, 2025.

ABSS - Foot Over Bridges (FOBs) - Part 2

Titwala FOB (LB-1941):

Cost: ₹10.31 Cr | Status: 2% complete.
Remarks: GAD approved. Foundation work yet to start. Material under procurement. TDC: Dec 31, 2025.

Diva FOB (LB-1966):

Cost: ₹16.77 Cr | Status: 5% complete.
Remarks: Piling work for foundation is 75/162 complete. Column and girder fabrication yet to start. TDC: Feb 28, 2026.

Chinchpokli FOB & Roof Plaza (LB-1970):

Cost: ₹40.16 Cr | Status: 0% complete.
Remarks: Detailed estimate vetted. Tender under preparation.

ABSS - Lifts & Escalators

Lifts (Sugamya Bharat Abhiyan Ph-II) (LB-1952):

Cost: ₹14.30 Cr
Status: LOA Issued.
Remarks: LOA issued on March 3, 2025, for 20 Lifts. Work has not yet started.

Escalators (LB-1955):

Cost: ₹48.05 Cr
Status: TC Proceedings under process.
Remarks: Tender for 30 escalators was re-invited. Financial Bid opened on March 13, 2025. TCP is under process.

ABSS - Toilets & STPs

Project 1: Toilets at VVH, VK, KJM, MBQ, DW (LB-1944):

Cost: ₹6.52 Cr | Status: 60% complete.
Remarks: Toilets completed at VVH, VK, and MBQ. Work in progress at KJM and DW.

Project 2: Toilets at TLA, SHD, IGP, VDLR, SNRD (LB-1945):

Cost: ₹6.06 Cr | Status: 100% complete.

Project 3: Toilets at BY, CHG, MTN, CLA, PR (LB-1946):

Cost: ₹6.00 Cr | Status: 100% complete.

Project 4: Provision of 25 STPs at 15 Stations (LB-1936):

Cost: ₹7.05 Cr | Status: 85% complete.
Remarks: STPs completed at 13 locations. Work in progress at Diva.

ABSS - Telecom & Electrical Works

ProjectCost (₹ Cr)StatusTDC
Passenger Information System (Video) (LB-1953)7.3056% completeJuly 31, 2025
Public Announcement System (LB-1954)6.1556% completeJuly 31, 2025
Telecom Assets & Backbone Connectivity (LB-1968)9.0078% complete-
Cable Trays & Ventilation System (LB-1951)6.9950% completeAug 31, 2025
Signage (LB-1956)3.0450% completeAug 31, 2025

ABSS - Horticulture & Divyangjan Facilities

Horticulture (Group 1: SNRD, VDLR, PR, MTN, CLA) (LB-1938):

Cost: ₹5.80 Cr | Status: 50% complete.
Remarks: Vertical gardens completed at Parel, VDLR, Matunga. Work in progress at Kurla.

Horticulture (Group 2: 10 other stations) (LB-1939):

Cost: ₹9.85 Cr | Status: 50% complete.
Remarks: Work completed at Byculla and Chinchpokli. In progress at others.

Flooring for Divyangjan (LB-1969):

Cost: ₹11.83 Cr | Status: 70% complete.
Remarks: Flooring work is in progress at all 15 stations.

Section 4

General Passenger Amenities

Progress on FOBs, Lifts, Platforms, and Other Works

Legacy FOBs (2015-18 Sanctions) - Mostly Complete

Multiple FOB projects sanctioned prior to ABSS are now complete, significantly improving station accessibility.

  • Masjid FOB (2015-16): 100% complete.
  • Neral FOB (2015-16): 100% complete. Proposed for deletion.
  • LTT FOB (2016-17): 100% complete.
  • MRVC FOBs at 12 Stations (2017-18): 84% complete. FOBs at 10 stations are finished. Dadar GAD is under approval; Ulhasnagar work is pending.
  • FOBs at Kalva, Diva, Dombivali, Thakurli (2018-19): 100% complete.
  • FOBs at Ambernath, Shelu, etc. (2018-19): 100% complete, proposed for short closure as Ambernath FOB was handed over to MRVC.

Ongoing FOBs & FOB Improvement Works

ProjectCost (₹ Cr)StatusTDC
Somathane & Jite FOBs (LB-1923)3.642% completeJune 30, 2026
Khandala FOB Replacement (LB-1930)3.1175% completeDec 31, 2025
FOB Roofing/Surface Improvement (BY-KOPR Sec) (LB-1924)4.3149% completeDec 31, 2025
Igatpuri FOB Extension (LB-2163)4.590% completeJune 30, 2026

Dadar Station - Multiple Improvement Works

Dadar station is seeing a cluster of targeted improvement works to de-congest and improve amenities.

Project IDShort DescriptionCost (₹ Cr)StatusTDC
LB-1971Widening of PF No.1/2.2.39100%Completed
LB-1976Modification of stairs/ramps on PF 5.2.40100%Completed
LB-1972Relocation of GRP office on PF 3/4.2.3885%31-Dec-25
LB-1973Relocation of overhead offices on PF 3/4.2.3979%31-Dec-25
LB-1982COP at additional width of PF1/2.2.4485%31-May-26
LB-1983COP at uncovered portion on PF 5.1.9971%31-Dec-25
LB-1975Extension of existing lattice FOB.2.470%31-May-26

Platform Improvements - Raising & Resurfacing

  • Project: Raising/resurfacing of PFs at Dadar, Govandi, Bhandup, Thane, etc. (LB-1934)
    Cost: ₹3.13 Cr | Status: 62% complete | TDC: Dec 31, 2025.
  • Project: Improvement to platform surface at Kalyan (PF 1, 1A, 2/3, 6/7) (LB-1989)
    Cost: ₹2.30 Cr | Status: 35% complete | TDC: Dec 31, 2025.
  • Project: Improvement to platform surfacing at Ghatkopar (PF 1, 2/3, 4) (LB-1978)
    Cost: ₹1.79 Cr | Status: 61% complete | TDC: Dec 31, 2025.

Platform Improvements - Cover Over Platform (COP)

ProjectCost (₹ Cr)StatusTDC
Improvement to COP at Dombivali (PF 5 & 3/4) (LB-1984)2.1592% completeJune 30, 2025
Improvement to COP at Bhandup (PF 1, 2/3, 4) (LB-1986)2.0285% completeJuly 31, 2025
Improvement to COP at Mulund (PF 1, 2/3, 4) (LB-1987)2.2370% completeDec 31, 2025
Improvement to COP at Thane (PF 1, 2, 3/4) (LB-1985)2.3580% completeDec 31, 2025
COP at Lonavala extended portion (PF 1) (LB-1990)2.4875% completeJune 30, 2025

Platform Improvements - Other Works

  • Kopar - Provision of home PF (LB-1892): Cost: ₹10.11 Cr | Status: 100% complete. Proposed for deletion.
  • Nahur - Provision of Home platform (LB-1922): Cost: ₹6.96 Cr | Status: 42% complete. | TDC: March 31, 2026.
  • Bhiwandi Road - Extension of PF 2/3 (LB-1921): Cost: ₹5.45 Cr | Status: 100% complete.
  • Kurla - Extension of PFs 3/4, 5/6, 7/8 (LB-1977): Cost: ₹2.42 Cr | Status: 20% complete. | TDC: Dec 31, 2025.

Lifts (Non-ABSS)

Project: Provision of 52 nos. Lifts (Central Railway) (LB-1905)

Sanction Year: 2018-19
Cost: ₹24.56 Cr
Status: 12% complete.
Remarks: Zonal work. HQ to comment on division-specific progress.

Project: Provision of 77 nos. Lifts (Central Railway) (LB-1904)

Sanction Year: 2018-19
Cost: ₹36.42 Cr
Status: 60% complete.
Remarks: Mumbai Division: 41 of 65 lifts commissioned.

Emergency Medical Rooms (EMRs)

  • Project: EMR at 8 stations (Bhandup, Kalwa, etc.) (2016-17): Cost: ₹0.99 Cr | Status: 100% complete.
  • Project: EMR at 5 stations (Byculla, Sion, etc.) (2016-17): Cost: ₹0.63 Cr | Status: 100% complete.
  • Project: EMR at 24 stations (CSMT, Parel, etc.) (LB-1893): Cost: ₹4.59 Cr | Status: 17% complete. | Remarks: Contract terminated. Estimate under revision. Proposed for short closure.

Water Supply & Water Tank Works

  • Igatpuri Station Water Supply (LB-1913): Cost: ₹1.37 Cr | Status: 35% complete. TDC: March 31, 2026.
  • Water Facilities at KJT-KHPI & PNVL-KJT sections (LB-1925): Cost: ₹3.69 Cr | Status: 92% complete. TDC: Dec 31, 2025.
  • Replacement of Unsafe Water Tanks (New Works 2023-24):
    • CSMT (NAB/Annex Bldg): 78% complete.
    • Kurla Diesel Shed: 19% complete.
    • LTT: 40% complete.
    • Kurla Carshed: 41% complete.

Ballastless Track & Washable Apron Works (New)

ProjectCost (₹ Cr)Status
Ballastless Track at Panvel (PF 5, 6, 7) (2024-25)14.65Under Finance Vetting
Washable Apron / BLT at CSMT (PF 8, 9, 15, 16) (2024-25)18.56Estimate under preparation
Washable Apron / BLT at Dadar (PF 13, 14) (2024-25)7.64Estimate under preparation
Washable Apron / BLT at LTT (PF 1, 2, 3) (2024-25)19.01Estimate under preparation
Ballastless Track at Dadar, Kurla, Thane, Dombivli (2024-25)15.10Estimate under preparation

Train Management System (TMS) - A Major Upcoming Initiative

Seven new works have been sanctioned in the 2024-25 budget for the provision of TMS and associated station equipment across various sections of Mumbai Division.

SectionEstimated Cost (₹ Cr)
CSMT - PNVL18.73
TNA - KYN17.38
Trans Harbour & BEPR - Uran15.18
CSMT - MTN19.31
Sion - TNA18.62
KYN - LNL19.50
KYN - IGP18.90
Total Cost₹127.62 Crores

Current Status: Detailed Estimates for all seven works are under preparation.

WIP Deep Dive - Chikhloli Station Construction

Project 1: Platform, COP, FOB, Track Works (LB-1907)

Cost: ₹10.02 Cr | Status: 11% complete.

Project 2: Station Bldg, Booking Office, Water Supply (LB-1908)

Cost: ₹5.94 Cr | Status: 9% complete.

Executing Agency: MRVC (as part of MUTP-IIIA)

Remarks: Land acquisition is complete. The main contract has been awarded, and work is in its initial stages.

Target Completion Date (TDC): December 31, 2026.

WIP Deep Dive - Kalyan Indicators (LB-1910)

  • Project Name: Kalyan: Replacement of suburban indicators and Coach Guidance display Boards with graphical type LED display based on RDSO Spec.
  • Cost: ₹2.96 Cr
  • Status: 65% complete
  • Agency: S&T
  • Remarks: 90% installation work is complete. Some material like HDPE pipe, NVR IP camera, modem, router etc. are pending for supply. Some installation issues to be resolved.
  • TDC: May 31, 2025

WIP Deep Dive - Atgaon Elevated Booking Office

  • Project ID: 01.02.53.21.4.51.007
  • Project Name: Atgaon-Provision of Elevated Booking Office at Atgaon station.
  • Cost: ₹0.39 Cr
  • Status: 16% complete
  • Agency: Engineering
  • Remarks: Contract awarded. Scope includes new elevated booking office on UP line side and dismantling of old booking office. Foundation excavation Work completed. Structural design approval is in progress.
  • TDC: December 31, 2025

WIP Deep Dive - Lonavala Station Upgradation (DN Side)

  • Project ID: 01.02.53.22.1.51.002
  • Project Name: Lonavla:- Upgradation of Lonavla station on DN side by development circulating area, approach road and parking area etc.
  • Cost: ₹3.49 Cr
  • Status: 99% complete
  • Agency: Gati Shakti Unit (GSU)
  • Remarks: Work is physically complete. Final bill is under preparation.
  • TDC: Completed

WIP Deep Dive - Nahur Home Platform

  • Project ID: 01.02.53.22.1.51.011
  • Project Name: Nahur (SG-2): Provision of Home platform
  • Cost: ₹6.96 Cr
  • Status: 42% complete
  • Agency: Engineering
  • Remarks: Platform coping wall completed. RCC flooring, RCC walling & COP columns erection is in progress.
  • TDC: March 31, 2026

WIP Deep Dive - Improvement to Circulating Area

  • Project ID: 01.02.53.22.1.51.003
  • Project Name: Improvement to circulating area & road from Chhatrapati Shivaji Maharaj Terminus to Kalyan & King Circle to Mankhurd Stations.
  • Cost: ₹14.15 Cr
  • Status: 95% complete
  • Agency: R (RLDA/MRVC)
  • Remarks: Work completed at Chunabhatti, Mankhurd, LTT, Mulund, Thane, Kopar, Thakurli & Kalyan. Further work is in progress.
  • TDC: June 30, 2025

WIP Deep Dive - FOB Roofing System Improvement

  • Project ID: 01.02.53.22.1.51.008
  • Project Name: BY–KOPR Sec. :- Impro. of roofing system and surface of FOB’s including addl./impr./reconstr. to staircase.
  • Cost: ₹4.31 Cr
  • Status: 49% complete
  • Agency: Engineering
  • Remarks: Strengthening of FOB staircase completed at Mulund PF-1, Vikhroli, Ghatkopar & Matunga. Further strengthening of staircase is in progress at Parel, Chinchpokali, Mulund PF-2/3.
  • TDC: December 31, 2025

WIP Deep Dive - Architectural Consultancy for ABSS

  • Project ID: 01.02.53.22.3.55.004
  • Project Name: Architectural consultancy for 15 Railway station of Mumbai division in Amrit Bharat Station Scheme.
  • Cost: ₹1.68 Cr
  • Status: 90% complete
  • Agency: Gati Shakti Unit (GSU)
  • Remarks: Architectural consultancy for all 15 Railway stations have been awarded. Plans for all 15 stations of ABSS finalised and approved by DRM. Work in progress.
  • TDC: June 30, 2025

WIP Deep Dive - Dadar GRP Office Relocation

  • Project ID: 01.02.53.23.3.51.015
  • Project Name: Dadar (NSG 1) :– Relocation of existing GRP office on PF 3/4 for de-congestion at CSTM end.
  • Cost: ₹2.38 Cr
  • Status: 85% complete
  • Agency: Engineering
  • Remarks: Detailed estimate sanctioned. Construction of new GRP office on PF-6 is in progress.
  • TDC: December 31, 2025

WIP Deep Dive - Lonavala COP Extension

  • Project ID: 01.02.53.23.3.51.022
  • Project Name: Lonavla (NSG 3): - Provision of COP on extended portion of PF 1 (190 M) and other passenger amenities at PA end.
  • Cost: ₹2.48 Cr
  • Status: 75% complete
  • Agency: Engineering
  • Remarks: Foundation and columns erection completed. Roofing work is in progress.
  • TDC: June 30, 2025

Section 5

Project Pipeline, Closures & Deletions

Streamlining the Project Portfolio

Works Proposed for Deletion

10 works are proposed for deletion. These projects are 100% physically complete, and their final bills have been passed. This is a crucial administrative step to clean the records.

SNSanction YearShort Name of Work
12015-16Neral FOB Replacement
22018-19KOPAR - Provision of home PF
32018-19Thane - Addl. floor on parking structure
42018-19Nilje/NGTN/PEN - Office Improvements
52022-23Kalyan - PF shelter on dismantled portion
62022-23Launching of ‘One Station One Product’ Scheme
72022-23Improvement of booking/parcel/goods office furniture
82021-22Kalyan - Mainline indicators
92021-22Improvement of Divyangjan facility (audio beeper)
102021-22Augmentation of IP based Central Announcement system

Works Proposed for Short Closure

5 key works are proposed for short closure. This occurs when the full scope is no longer required, often because it has been merged with a larger, newer project.

  1. New Booking Offices (LB-1888): Reason: Work at Currey Road & Karjat dropped due to site unavailability.
  2. Emergency Medical Rooms at 24 stations (LB-1893): Reason: Contract terminated for slow progress. The remaining work will be done under a revised estimate/new tender.
  3. FOB at Khadavali, etc. (LB-1895): Reason: FOB at Khadavali will now be done by the Construction Organization as part of the 3rd & 4th line project.
  4. FOB at Ambernath, etc. (LB-1896): Reason: Ambernath FOB is now part of the MRVC 3rd & 4th line project.
  5. Provision of TC Office (2021-22): Reason: Scope at most stations is now covered under ABSS works.

The New Works Pipeline - At Estimation Stage

A strong pipeline of 40 new projects ensures continuous development. These are currently in the estimation or finance vetting stage.

StatusNo. of WorksKey Projects Include
Under Finance Vetting14Parcel Depots (WB), Goods Shed (TPND), Ballastless Track (Panvel), Multi-level parking (Dombivali), ABSS Ph-II works (Panvel, Thakurli)
Under Preparation26TMS (7 works), Washable Aprons (CSMT, DR, LTT), Goods Shed (Trombay), New COPs, Station Upgrades (Karjat, Roha)

The New Works Pipeline - At Tender/Approval Stage

11 works have moved beyond estimation and are in advanced pre-execution stages.

StatusNo. of WorksKey Projects Include
LOA Issued3Lifts (ABSS), Information Boards, Drinking water booths.
TC Proceedings / Tender Floated4Kalyan Goods Shed, Escalators (ABSS), CSMT Indicators, Dadar Ramp.
GAD under Approval4FOBs at Somathane, Jite, Dadar, Igatpuri; Chinchpokli ABSS work.

Financial Allocation Summary

Financial Snapshot - Key Allocations (Figures in ₹ Lakhs)

Project NameOriginal CostAnticipated CostExpenditure Upto DateOutlay 2025-26Balance
CSMT Upgradation18,13,00018,13,0004,91,4904,00,0009,41,830
MRVC FOBs (12 Stns)1,34,3601,37,3601,26,52010,000839
ABSS Escalators48,05047,5753,6012,00042,189
ABSS Lifts14,30014,2901535,0009,173
Kalyan Goods Shed23,05023,050050022,550
Turbhe Goods Shed13,27914,9794,47690014,073

Section 6

Conclusion

Key Achievements

  • Significant Completions: 47 projects are physically complete, directly benefiting passengers and freight customers.
  • ABSS Momentum: The Amrit Bharat Station Scheme is well underway, with 5 stations already completed and many others in advanced stages, promising a visible transformation.
  • Strategic Project Initiation: Landmark projects like the CSMT redevelopment have been successfully launched.
  • Portfolio Management: Proactive steps are being taken to clean up records by proposing the deletion and short closure of legacy projects.
  • Robust Pipeline: A healthy pipeline of 40 new works ensures that the pace of development will continue.

Way Forward - Key Focus Areas

  1. Expedite High-Impact Projects:
    • Closely monitor the CSMT Redevelopment project to ensure milestones are met.
    • Prioritize the tendering and awarding of contracts for the remaining ABSS works, especially escalators.
    • Accelerate the execution of Goods Shed projects at Kalyan, Turbhe, and Nagothane.
  2. Resolve Bottlenecks in WIP:
    • Address the issues leading to the termination of contracts for EMRs and Booking Offices and ensure swift re-tendering.
    • Follow up on GAD approvals for critical FOBs to move them into the execution phase.
  3. Streamline New Projects:
    • Fast-track the estimate preparation and vetting for the 40 new works, especially the Train Management System (TMS) projects.
  4. Administrative Efficiency:
    • Complete the process of deleting and short-closing all identified works to ensure accurate reporting and financial management.